| CASE STUDIES
 |
 |
| |
U.S. Steel's 22
MW
Topping Turbine (click on photo to enlarge) |
| |
|
22 MEGAWATT TOPPING
TURBINE INSTALLATION - U.S. STEEL
How did rem
ENGINEERING
generate 22 megawatts from an 8 Megawatt opportunity?
The Fairfield Works of United States Steel, located in Birmingham,
AL, recognized an opportunity to generate eight (8) Megawatts
of electricity. The mill was reducing pressure and desuperheating
steam from 900 psig, 900°F to 325 psig, 600°F. The
quantity of steam reduced would generate 8.0 megawatts of
electricity. rem ENGINEERING
maximized this generation opportunity, justifying the installation
of a 22.0 MW topping turbine.
The production of blast furnace gas
is necessary to the steel making process at the Fairfield
Works. Excess gas, considered "free" fuel, is burned
in boilers to produce steam. Common practice in the steel
industry is to generate electricity with the steam produced
in the boilers by utilizing steam turbines. The object is
to maximize the electric generation with the limited excess
blast furnace gas available.
The installation of a closed feedwater
heater and increased high pressure steam production are the
keys to the almost 3X improvement made by rem
ENGINEERING.
The effect of the closed feedwater heater is increased steam
flow through the topping turbine. Steam exiting from the turbine
is used to heat boiler feedwater thus increasing steam production
in the boiler. Electrical generation is therefore increased
with no additional fuel required. To take maximum advantage
of the proposed cycle modification, the Fairfield Works power
group made every effort to increase high pressure steam production
and reduce low pressure steam production.
ˆ back to top |
back to Case Studies
|