|
CASE STUDIES
Feed the Children is a charity dedicated to feeding children
around the world. They recently acquired a new distribution
center in Elkhart, Indiana. This distribution center was formally
a Bayer manufacturing and warehousing facility having an enclosed
area of approximately one million square feet.
 |
 |
| |
Feed the Children's
Distribution Center (click on photo to enlarge) |
| |
|
The heating and air conditioning system was massive and far
too costly to operate. There was excessive boiler and compressed
air capacity. An estimate to reconfigure and update the system
indicated a cost of over $5,000,000.00. At this point, rem
ENGINEERING was contacted and asked
to confirm the price and suggest ways to reduce this high
cost.
The existing cooling system was comprised of over 8,000 horse
power of ammonia compressors, far more than was required.
We replaced the entire ammonia system with modern chillers.
We reduced the installation cost by placing the units on the
roof of the ammonia compressor building. The steel support
structure cost was virtually eliminated by using steel formally
used to support cooling towers required for the ammonia system.
We installed a new fire tube boiler to meet the reduced needs
replacing the over 400,000 lb/hr of steaming capacity. The
boiler was sited in the building to take maximum advantage
of the existing steam and fuel lines. The boiler system included
zeolite softeners to replace a hot lime system and a new deaerator
with boiler feed pumps. The deaerator was also connected into
the condensate return system. The out dated air compressors
were replaced by a single screw compressor and air drying
system.
The final bill for all required equipment installed was less
than 40% of the original estimated costs. The required air
permits were obtained and all equipment placed in service
on schedule. References are available for this project. Please
contact rem ENGINEERING.
ˆ back to top |
back to Case Studies
|